Pandemic Greenfield Manufacturing Facility

Contract Pharma | North Carolina

This major CDMO client hired PROTECS to complete the design and construction of a 156,000-square-foot facility for the Department of Defense (DOD). The $127 million project is a new pandemic greenfield building that has three floors, plus a penthouse. The project consisted of incoming sampling/dispensing, two liquid vial filling lines, two lyophilization areas, compounding area, parts wash and autoclave area, cold rooms storage, freezer room, IT/data room, automated vial inspection line, lab area, cGMP warehouse, WIP storage, locker/gowning, administration, café, cafeteria, and mechanical/process support spaces. The new building also required new HVAC, compressor, chilled water, DI water, WFI systems, clean steam, N2 distribution system, waste handling, and emergency power systems (UPS).

Quick Facts

Size

156,000 SF

Total Project Value:

$127 MM

Project Delivery Method

Design / Build / Consulting / Commissioning

Services

  • Conceptual Evaluation / Design

  • Project Cost Estimating

  • Project Schedule Analysis

  • Construction Management

  • Commissioning

Critical Project Demands

  • New incoming utilities and parking constraints on site.

  • Working on an existing campus.

  • Extremely tight timeline due to being a pandemic site.

  • Rigging and installing of process equipment as it arrives

    from overseas.

  • Relocated the project from an interior fit-out in the NE to

    a greenfield site in NC.

  • Coordinating and constructing the first greenfield project

    on the site in over 10 years.

  • Overcoming poor site sub-soil conditions and old

    unknown foundation remnants.

  • Changing the process program for the virus type in the

    middle of construction.

  • Resetting the project to align with the client’s client on

    multiple occasions after commencing construction.